Package # SC-MIN-12-206 QBE Nomination Closing Date March-01-12
Title Process Tanks internal re-coating Tender Issue Date February-27-12
    Bid Closing Date March-14-12

For more information contact: Bill Ivany
709-752-7509
709-896-6437
click here to send email

Contract Scope

SCOPE OF WORK

2.1       General

The Contractor will be responsible for field verification of dimensions, locations, and clearances prior to commencing the work.  All interferences which directly or indirectly affect the required works of this project are to be communicated to the Company.

The Contractor is to take all necessary measures to complete the required works of this project without interfering with the Company’s daily operations.  In this case, the work will be completed during an extended Concentrator shutdown in June  2012. 

All products and materials to be supplied by the Contractor shall be new and shall meet all requirements of this specification.